Multiple Choice
The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead at 100% production capacity. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual fixed overhead was $360,000 and actual variable overhead was $170,000. Actual production was 11,700 units. Compute the factory overhead volume variance.
A) $9,000F
B) $9,000U
C) $5,500F
D) $5,500U
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Financial reporting systems that are guided by
Q38: The standard cost is how much a
Q72: Standard cost variances are usually not reported
Q114: The St. Augustine Corporation originally budgeted for
Q115: The following data is given for the
Q117: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2013/.jpg" alt=" Calculate the variable
Q118: The following data relate to direct labor
Q122: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2013/.jpg" alt=" Calculate the Direct
Q123: If the price paid per unit differs
Q124: Trumpet Company produced 8,700 units of product