menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Successful Project Management Study Set 1
  4. Exam
    Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence
  5. Question
    The Work Breakdown Structure Is the Same Thing as the Project
Solved

The Work Breakdown Structure Is the Same Thing as the Project

Question 105

Question 105

True/False

The work breakdown structure is the same thing as the project organization chart or structure.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q100: A task is a piece of work

Q101: The customer requirements section should also include

Q102: Quality of the project deliverables should be<br>A)

Q103: The success of the project<br>A) is guaranteed

Q104: It is essential to wait until the

Q106: _ separate(s)the planning and scheduling functions.<br>A) Gantt

Q107: In many cases, the customer states high-level

Q108: One of the major drawbacks to the

Q109: The project objective should be<br>A) set and

Q110: Planning for quality is a necessary, yet

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines