Multiple Choice
The ____ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.
A) statement of work
B) project scope document
C) network diagram
D) work breakdown structure
Correct Answer:

Verified
Correct Answer:
Verified