Multiple Choice
Once the project scope document has been prepared and agreed on, the next step in the planning phase is to
A) monitor and control the quality to assure acceptance.
B) create a detailed work breakdown structure.
C) begin work on the project.
D) prepare and approve the contract.
Correct Answer:

Verified
Correct Answer:
Verified