Multiple Choice
Designating ____ as having primary responsibility can cause confusion and increase the risk that some work will "fall through the cracks," because each may assume that the other is going to do it.
A) a subcontractor
B) a third party
C) two or more individuals
D) the project manager
Correct Answer:

Verified
Correct Answer:
Verified