Multiple Choice
____ in a network diagram will allow the project to be completed in the shortest possible time while making the best use of available resources (the experts) .
A) Looping
B) Laddering
C) Layering
D) Serially listing
Correct Answer:

Verified
Correct Answer:
Verified