Multiple Choice
The earliest start time for a specific activity must be ____ the latest of all the earliest finish times of all the activities leading directly into that specific activity.
A) earlier than
B) the same as
C) the same as or later than
D) later than
Correct Answer:

Verified
Correct Answer: