Multiple Choice
As the project progresses, the actual finish times (AFs) of completed activities will determine
A) the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
B) the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
C) the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
D) the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.
Correct Answer:

Verified
Correct Answer:
Verified
Q50: The latest finish time for a specific
Q51: The _ time is the shortest estimated
Q52: Once this baseline plan is agreed upon
Q53: At the beginning of a longer-term project,
Q54: The contractor may not want to commit
Q56: The sponsor or customer often states the
Q57: An updated project schedule can be generated
Q58: The estimated duration should be aggressive and
Q59: Changes requested early in the project always
Q60: Positive slack indicates the maximum amount of