Solved

As the Project Progresses, the Actual Finish Times (AFs)of Completed

Question 55

Multiple Choice

As the project progresses, the actual finish times (AFs) of completed activities will determine


A) the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
B) the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
C) the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
D) the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions