Multiple Choice
Activities can be delayed only to the point where all their positive slack is used up, as any further delays would cause the project to
A) increase costs of all the activities in the project.
B) extend beyond the project completion time.
C) be completed ahead of schedule.
D) increase its requirements for additional resources for all activities.
Correct Answer:

Verified
Correct Answer:
Verified