Multiple Choice
When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:
A) activities that will be performed in the near term.
B) activities that will be performed in the towards the end of the project.
C) activities that will be performed at the end of the project.
D) all the activities in the project.