Multiple Choice
During project closing, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that
A) they can be stored easily.
B) they can be readily retrieved for future use.
C) the files are ready for audit.
D) the project sponsor could review them.