menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 3: Project Phases and Organization
  5. Question
    A Score of 1 in the Darnall-Preston Complexity Index Indicates
Solved

A Score of 1 in the Darnall-Preston Complexity Index Indicates

Question 65

Question 65

True/False

A score of 1 in the Darnall-Preston Complexity Index indicates the lowest level of complexity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q60: What are the various tasks performed by

Q61: Confirming or developing conceptual schedules and budgets

Q62: The Darnall-Preston Complexity Index DPCI) ranks complexity

Q63: The DPCI score for size would be

Q64: Explain the five DPCI scores for size.

Q66: The _ phase of a project life

Q67: The _ phase, labeled by PMI as

Q68: Which of the following project functions undertakes

Q69: The technological complexity for a project reflects

Q70: The technological complexity for a project reflects

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines