Confirming or Developing Conceptual Schedules and Budgets Usually Takes Place

Question 61

Multiple Choice

Confirming or developing conceptual schedules and budgets usually takes place during the _____ phase of the project life cycle.


A) planning
B) initiation
C) closeout
D) execution
E) maintenance

Correct Answer: