Multiple Choice
A, Inc., enters into a contract with B Service to fix A's precisely engineered molding equipment. If B delays the repair for five days, knowing that A will lose a certain percentage of profit for the delay, A might be awarded consequential damages to
A) establish, as a matter of principle, that B acted wrongfully.
B) provide A with funds for a foreseeable loss beyond the contract.
C) provide A with funds for its loss of the bargain.
D) punish B and set an example to deter others from similar acts.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: Whether a contract's limitation-of-liability clause will be
Q30: A party seeking to recover compensatory damages
Q31: Punitive damages are never awarded in breach
Q33: Earl holds 1,000 pounds of perishable fruit
Q33: Fact Pattern 18-B1 <br>A enters into a
Q34: Beachside Pools, Inc., agrees to build a
Q35: Value Acquisitions, Inc., contracts to buy Wobbling
Q36: Grady enters into a contract to buy
Q37: To avoid liability for intentional injuries, Vermont
Q39: Rite Contractors,Inc.,agrees to build a motel for