Multiple Choice
Given W = D * U for an effort-driven task.Assume an 8-hour workday.Initially,task R was assigned to Bob.Bob was expected to accomplish 32 hours of work in five days.If Bob were 100 percent available to work on task R during the entire five days,his efficiency rate is __________%.
A) 80
B) 70
C) 60
D) 75
Correct Answer:

Verified
Correct Answer:
Verified