Multiple Choice
Given W = D * U for an effort-driven task.Assume an 8-hour workday.Initially,task R was assigned to Bob.Bob was expected to accomplish 32 hours of work in five days.Bob was expected to be 100% available to work on task R during the entire five days.However,Bob left the company and will be replaced by Sam.Sam's efficiency rate is 90%.If Sam is only 70% available,Sam will require __________ hours to complete task R.
A) 63
B) 40
C) 53.2
D) 50.8
Correct Answer:

Verified
Correct Answer:
Verified
Q2: If a contradiction or conflict between constraints
Q7: If a predecessor activity finishes early,will the
Q9: The _ heuristic provides a general solution
Q11: In some situations,two activities are scheduled to
Q21: The use of _ activity time estimates
Q24: The _ technique overlaps the design and
Q31: Discuss some other causes of the strong
Q32: Which of the following effects will be
Q42: Discuss the advantages obtained from resource leveling.
Q50: The standard practice with AOA and AON