Multiple Choice
In some situations,two activities are scheduled to be carried out in parallel and using the same scarce resource.If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously,then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.
A) duration
B) slack
C) float
D) buffer
Correct Answer:

Verified
Correct Answer:
Verified