Solved

In Some Situations,two Activities Are Scheduled to Be Carried Out

Question 11

Multiple Choice

In some situations,two activities are scheduled to be carried out in parallel and using the same scarce resource.If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously,then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.


A) duration
B) slack
C) float
D) buffer

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions