In a network,if the delay of an activity will delay completion of the project,the activity is called a(n) __________.


A) valuable
B) efficient
C) critical
D) noteworthy

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18: What type of time estimates are used

Q19: In the AOA network,arrows depict _.<br>A)networks<br>B)events<br>C)activities<br>D)dummy activities

Q20: The shortest time in which the entire

Q21: The variance of a population is a

Q22: Describe the benefits of forming a network

Q24: _ have a weakness of being difficult

Q25: A(n)_ is a specific task or set

Q26: Assume that task J has a most

Q27: Task F has duration of 10 days

Q28: Slack is also known as _.<br>A)critical path<br>B)scope<br>C)float<br>D)precedence

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines