Multiple Choice
Assume that task J has a most likely duration of 20 days,an optimistic duration of 13 days,and a pessimistic duration of 30 days.If the optimistic and pessimistic durations are 95 percent estimates,the standard deviation for task J is ________ days.
A) 5.167
B) 5
C) 4.67
D) 3.2