Multiple Choice
One of the challenges project managers face is to ensure that managers do not mix __________.
A) outcomes with the specific tasks needed to produce them
B) project milestones with their respective completion dates
C) outside interests' requirements with organizational expectations
D) control limits with specifications
Correct Answer:

Verified
Correct Answer:
Verified