Question 20

Question 20

True/False

A Web site developer negotiates a contract to develop a Web site for $2,000.This would be an example of a Fixed-Price/Lump-Sum contract

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: What is meant by full in-sourcing?

Q16: Not establishing an appropriate balance of power

Q17: What is the purpose of a contract?

Q18: The decision whether to purchase or outsource

Q19: A large number of organizations have had

Q21: What are some hidden costs of outsourcing?

Q22: _ has caused a lot of controversy

Q23: Outsourcing may be viewed as a more

Q24: Managing scope in terms of its definition

Q25: _ provides greater flexibility by allowing specific

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines