Managing Scope in Terms of Its Definition and Change Control

Question 24

Multiple Choice

Managing scope in terms of its definition and change control refers to which of the following Project Procurement Management processes?


A) Plan Procurements
B) Conduct Procurements
C) Administer Procurements
D) Close Procurements
E) Plan Exit Strategy