In Project Communications Management,ensuring That Clear,consistent,and Timely Communication Satisfies the Information
Multiple Choice
In Project Communications Management,ensuring that clear,consistent,and timely communication satisfies the information needs and that project stakeholder issues are resolved is _____.
A) identify stakeholders
B) plan communications
C) distribute information
D) manage stakeholder expectations
E) report performance