Multiple Choice
Estimate at Completion (EAC) is __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) how much we spent to complete the project
Correct Answer:

Verified
Correct Answer:
Verified
Q8: A _ describes the present state of
Q9: A metric that provides an estimate for
Q10: Earned Value tells us _<br>A) how much
Q11: Which of the following is not likely
Q12: What is the purpose of a project
Q14: Cost Variance (CV) = Earned Value -
Q15: EV-AC =<br>A) Cost performance index (CPI)<br>B) Scheduled
Q16: What is Actual Cost (AC)?
Q17: The Estimate At Completion (EAC) is a
Q18: What is a project review and what