Multiple Choice
Cost Variance (CV) is __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) the difference between the estimated cost and how much we have actually spent
Correct Answer:

Verified
Correct Answer:
Verified