Multiple Choice
Earned Value tells us __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
Correct Answer:

Verified
Correct Answer:
Verified
Q5: The Expected Time Complete (ETC) provides an
Q6: The project manager must have a clear
Q7: What is Budget at Completion (BAC)?
Q8: A _ describes the present state of
Q9: A metric that provides an estimate for
Q11: Which of the following is not likely
Q12: What is the purpose of a project
Q13: Estimate at Completion (EAC) is _<br>A) how
Q14: Cost Variance (CV) = Earned Value -
Q15: EV-AC =<br>A) Cost performance index (CPI)<br>B) Scheduled