Solved

The Budgeted Cost of Work Scheduled for an Activity or Component

Question 52

Multiple Choice

The budgeted cost of work scheduled for an activity or component of the WBS is the _____.


A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)

Correct Answer:

verifed

Verified