Multiple Choice
The 100 percent rule relates to___
A) the next level decomposition of a WBS element must represent 100 percent of the work applicable to the parent element.
B) clearly defining 100 percent of deliverables before beginning the project.
C) ensuring that project requirements remain fully static over the course of the project.
D) everyone's project performance will impact the project.
E) resource requirements needed to complete the project.
Correct Answer:

Verified
Correct Answer:
Verified