Multiple Choice
Lemaire Products reports the following information about resources.At the beginning of the year,Lemaire estimated it would spend $8,000 for energy and $12,000 for repairs. Compute unused resource capacity for repairs for Lemaire Products.
A) $2,400.
B) $12,000.
C) $6,000.
D) $3,600.
Correct Answer:

Verified
Correct Answer:
Verified