Services
Discover
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Accounting for Decision Making
Exam 13: Overhead and Marketing Variances
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 1
Multiple Choice
Which of these is true?
Question 2
Multiple Choice
Wendy Wall (WW) makes wall units. For the year, the following details have been budgeted. Output, 10,000 units; factory overheads $1,250,000, of which 60% is variable. Each wall unit should take 2.5 hours of direct labor to produce. WW produced 9,500 units with 24,000 DLH used and $1,175,000 actual overhead was incurred. Overhead is allocated based on direct labor hours (DLH) . What is Wendy's total overhead variance?
Question 3
Essay
Developing Additional Variances for Performance Evaluation Saidwell Company manufactures washers and dryers on a single assembly line in its main factory. The market has deteriorated over the last five years and competition has made cost control very important. Management has been concerned about the materials costs of both washers and dryers. There have been no model changes in the past two years, and economic conditions have allowed the company to negotiate price reductions for many key parts. Saidwell uses a standard cost system in accounting for materials. Purchases are charged to inventory at a standard price, and purchase discounts are considered an administrative cost reduction. Production is charged at the standard price of the materials used. Thus, the price variance is isolated at time of purchase as the difference between gross contract price and standard price multiplied by the quantity purchased. When a substitute part is used in production, a price variance equal to the difference in the standard prices of the materials is recognized at the time of substitution. The quantity variance is the actual quantity used compared with the standard quantity allowed, with the difference multiplied by the standard price. The materials variances for several of the parts Saidwell uses are unfavorable. Part #4121 is one item that has an unfavorable variance. Saidwell knows that some of these parts are defective and will fail. The failure is discovered during production. The normal defective rate is 5 percent of normal input. The original contract price of this part was $0.285 per unit; thus, Saidwell set the standard unit price at $0.285. The unit contract purchase price of Part #4121 was increased to $0.325 from the original $0.285 due to a parts specification change. Saidwell chose not to change the standard; it treated the increase in price as a price variance. In addition, the contract terms were changed from payment due in 30 days to a 4 percent discount if paid in 10 days or full payment due in 30 days. These new contractual terms were the consequence of negotiations resulting from changes in the economy. Data regarding the use of Part #4121 during December are as follows.
- Purchas es of Part $ 4121
- Unit price paid for purchases of Part # 4121
- Requisitions of Part 44121 from stores for use in products
- Substitution of Part # 5125 for Part # 4121 to use obsolete
stock (standard unit price of Part # 5125 is $ 0.35 )
- Units of Part $ 4121 and its substitute (Part # 5125) identified as defective
- Standard allowed usage 〈including normal defective units)
of Part 44121 and its substitute based on output for the month
\begin{array}{|l|}\hline\text{- Purchas es of Part \$ 4121 }\\\\\hline\text{- Unit price paid for purchases of Part \# 4121 }\\\hline\text{- Requisitions of Part 44121 from stores for use in products}\\\\\hline\text{- Substitution of Part \# 5125 for Part \# 4121 to use obsolete}\\\text{ stock (standard unit price of Part \# 5125 is \$ 0.35 )}\\\hline\text{- Units of Part \$ 4121 and its substitute (Part \# 5125) identified as defective}\\\\\hline\text{- Standard allowed usage 〈including normal defective units) }\\\text{of Part 44121 and its substitute based on output for the month}\\\hline\end{array}
- Purchas es of Part $ 4121
- Unit price paid for purchases of Part # 4121
- Requisitions of Part 44121 from stores for use in products
- Substitution of Part # 5125 for Part # 4121 to use obsolete
stock (standard unit price of Part # 5125 is $ 0.35 )
- Units of Part $ 4121 and its substitute (Part # 5125) identified as defective
- Standard allowed usage
〈
including normal defective units)
of Part 44121 and its substitute based on output for the month
150
,
000
units
$
0.325
134
,
000
units
24
,
000
units
9.665
units
153.300
units
\begin{array}{|r|}\hline 150,000 \\\text { units } \\\hline \$ 0.325 \\\hline 134,000 \\\text { units } \\\hline 24,000 \\\text { units } \\\hline 9.665 \\\text { units } \\\hline 153.300 \\\text { units } \\\hline\end{array}
150
,
000
units
$0.325
134
,
000
units
24
,
000
units
9.665
units
153.300
units
Saidwell's material variances related to Part #4121 for December were reported as follows:
Price variance
$
7.560.00
∪
Quantity variance
1.339.50
∪
‾
Total materials variances for Part
#
4121
$
8.899.50
∪
\begin{array} { | l | c | } \hline \text { Price variance } & \$ 7.560 .00 \cup \\\hline \text { Quantity variance } & \underline { 1.339 .50\cup} \\\hline \text { Total materials variances for Part } \# 4121 & \$ 8.899 .50 \cup\\\hline\end{array}
Price variance
Quantity variance
Total materials variances for Part
#4121
$7.560.00
∪
1.339.50
∪
$8.899.50
∪
Bob Speck, the purchasing director, claims the unfavorable price variance is misleading. Speck says that his department has worked hard to obtain price concessions and purchase discounts from suppliers. In addition, Speck says engineering changes in several parts have increased their prices, even though the part identification has not changed. These price increases are not his department's responsibility. Speck declares that price variances no longer measure purchasing's performance. Jim Buddle, the manufacturing manager, thinks the responsibility for the quantity variance should be shared. Buddle states that manufacturing cannot control quality associated with less expensive parts, substitutions of material to use up otherwise obsolete stock, or engineering changes that increase the quantity of materials used. The accounting manager, Mike Kohl, suggests that the computation of variances be changed to identify variations from standard with the causes and functional areas responsible for the variances. Kohl recommends the following system of materials variances and the method of computation for each:
Required: a. Discuss the appropriateness of Saidwell Company's current method of variance analysis for materials and indicate whether the claims of Bob Speck and Jim Buddle are valid. b. Compute the materials variances for Part #4121 for December using the system recommended by Mike Kohl. c. Who would be responsible for each of the variances in Mike Kohl's system of variance analysis for materials?
Question 4
Essay
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required for each product unit. Planned production for the period was set at 8,000 units. Manufacturing overhead for the period is budgeted at $204,000, of which 30 percent is fixed. The 26,200 hours worked during the period resulted in production of 8,500 units. Manufacturing overhead cost incurred was $220,500. Required: Calculate the following three overhead variances: 1. Overhead volume variance 2. Overhead efficiency variance 3. Overhead spending variance
Question 5
Essay
Derf Company applies overhead on the basis of direct labor hours. Two direct labor hours are required for each product unit. Planned production for the period was set at 9,000 units. Manufacturing overhead for the period is budgeted at $135,000, of which 20 percent is fixed. The 17,200 hours worked during the period resulted in production of 8,500 units. Manufacturing overhead cost incurred was $136,500. Required: Calculate the following three overhead variances: 1. Overhead volume variance. 2. Overhead efficiency variance. 3. Overhead spending variance.
Question 6
Essay
The following information is for the third quarter of this year:
Planned
Actual
Production
92
,
000
units
87
,
000
units
Direct labor hours
506
,
800
DL
hrs
380
,
000
DL
hrs
Fixed manufacturing
overhead
$
205
,
000
$
182
,
400
Variable
manufacturing
overhead
$
910
,
000
$
841
,
500
Standard direct labor
hour per unit
5.5
\begin{array} { | l | r r| rr| l | } \hline & { \text { Planned } } &&{ \text { Actual } } \\\hline \text { Production } & 92,000 & \text { units } & 87,000 & \text { units } \\\hline \text { Direct labor hours } & 506,800 & \begin{array} { l } \text { DL } \\\text { hrs }\end{array} & 380,000 & \begin{array} { l } \text { DL } \\\text { hrs }\end{array} \\\hline \begin{array} { l } \text { Fixed manufacturing } \\\text { overhead }\end{array} & \$ 205,000 & & \$ 182,400 & \\\hline \begin{array} { l } \text { Variable } \\\text { manufacturing } \\\text { overhead }\end{array} & \$ 910,000 & & \$ 841,500 & \\\hline \begin{array} { l } \text { Standard direct labor } \\\text { hour per unit }\end{array} & 5.5 & & & \\\hline\end{array}
Production
Direct labor hours
Fixed manufacturing
overhead
Variable
manufacturing
overhead
Standard direct labor
hour per unit
Planned
92
,
000
506
,
800
$205
,
000
$910
,
000
5.5
units
DL
hrs
Actual
87
,
000
380
,
000
$182
,
400
$841
,
500
units
DL
hrs
Required: Calculate the following three overhead variances: 1. Overhead volume variance 2. Overhead efficiency variance 3. Overhead spending variance
Question 7
Multiple Choice
Karpoff Kremes (KK) planned to sell 40,000 Kings at $20 each and 20,000 Kweens at $15 each. Actual sales of the former were 45,000 and 25,000 of the latter, at $19 and $16 respectively. Which is true of KK's mix variance?