True/False
The steps in the CPM project planning process are:
1. Specify each individual activity.
2. Sequence the activities.
3. Draw a network diagram.
4. Estimate the completion time for each activity.
5. Identify the critical path (longest path through the network).
6. Update the CPM diagram as the project progresses.