Multiple Choice
The critical path is the path through the project network in which none of the activities have _______, that is, the path for which ________ for all activities in the path.
A) sack / AS = FS and FE = FL
B) compression / CS = LS and CE = LF
C) better timed / LS = ES and LF = EF
D) crashed / SE = SL and FE = FL
E) slack / ES = LS and EF = LF
Correct Answer:

Verified
Correct Answer:
Verified