Multiple Choice
___________ is described as follows: The work breakdown structure, a listing can be made of all the activities in the project. This listing can be used as the basis for adding sequence and duration information in later steps.
A) Sequence the activities
B) Identify the critical path (longest path through the network)
C) Specify each individual activity
D) Draw a network diagram
E) Estimate the completion time for each activity