Delay in the Critical Path Delays the Project

Question 14

Multiple Choice

delay in the critical path delays the project. Similarly, to accelerate the project it is necessary to _________ the total time required for the activities in the critical path.


A) improve
B) expand
C) compress
D) increase
E) reduce

Correct Answer: