Multiple Choice
Becky works on the assembly line of a manufacturing company where she installs a component part for one of the company's products.She is paid $16 per hour for regular time and time and a half for all work in excess of 40 hours per week.
-Becky works 42 hours during a week in which there was no idle time.The allocation of Becky's wages for the week between direct labor cost and manufacturing overhead cost would be: