menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Management Science Quantitative Approach
  4. Exam
    Exam 9: Project Scheduling: Pertcpm
  5. Question
    We Identify the Critical Path of a Project as
Solved

We Identify the Critical Path of a Project as

Question 10

Question 10

Multiple Choice

We identify the critical path of a project as


A) any path that goes from the starting node to the completion node.
B) the combined time of all paths of the project.
C) the shortest path through the project.
D) the longest path through the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q5: Activities following a node<br>A)can begin as soon

Q6: Joe King has ambitions to be mayor

Q7: Shortening activity times,which is usually accomplished by

Q8: A project has the following activities,durations,costs,and precedence

Q9: A critical activity is<br>A)an activity that consumes

Q11: A critical activity can be part of

Q12: The critical path for this network is

Q13: When activity times are uncertain,an activity's most

Q14: When activity times are uncertain,total project time

Q15: The earliest start time rule<br>A)compares the starting

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines