A critical activity is


A) an activity that consumes no time but shows precedence between events.
B) a milestone accomplishment within the project.
C) an activity with zero slack.
D) the beginning of an event.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: National Oil Company (NATOCO)must plan the shutdown

Q5: Activities following a node<br>A)can begin as soon

Q6: Joe King has ambitions to be mayor

Q7: Shortening activity times,which is usually accomplished by

Q8: A project has the following activities,durations,costs,and precedence

Q10: We identify the critical path of a

Q11: A critical activity can be part of

Q12: The critical path for this network is

Q13: When activity times are uncertain,an activity's most

Q14: When activity times are uncertain,total project time

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines