Multiple Choice
When activity times are uncertain,
A) we assume they are normally distributed.
B) we start by calculating the optimistic,the most probable,and the pessimistic time estimates.
C) we use the most probable time.
D) we need to obtain at least four time estimates for each activity.
Correct Answer:

Verified
Correct Answer:
Verified