Marcy Fetter,a staff analyst at the Los Angeles plant of Computer Products Corporation,is assigned to the team that is developing the process design for producing an RFID sensor.The corporate planning group in San Jose,California,has contacted her and asked how confident the design group is about completing the project in 60 days.She has developed the following estimated time durations in days for the project:
Marcy Fetter,a staff analyst at the Los Angeles plant of Computer Products Corporation,is assigned to the team that is developing the process design for producing an RFID sensor.The corporate planning group in San Jose,California,has contacted her and asked how confident the design group is about completing the project in 60 days.She has developed the following estimated time durations in days for the project: ​   ​  a.Compute the expected time and variance for each activity. b.Determine the critical path and expected duration of the project. c.What is the probability that the project will take longer than 58 days to complete? d.Which path in the project network offers the greatest risk of overrunning a new deadline of 56 days? ​
a.Compute the expected time and variance for each activity.
b.Determine the critical path and expected duration of the project.
c.What is the probability that the project will take longer than 58 days to complete?
d.Which path in the project network offers the greatest risk of overrunning a new deadline of 56 days?

Correct Answer:

verifed

Verified

​ a. blured image ​ b. blured image ​ The critical path is A-D-H...