Creelman Company makes four products in a single facility. Data concerning these products appear below: The milling machines are potentially the constraint in the production facility. A total of 13,000 minutes are available per month on these machines.
-How many minutes of milling machine time would be required to satisfy demand for all four products?
A) 13,000
B) 11,600
C) 7,000
D) 15,000