Multiple Choice
The "V-model" of the waterfall method is BEST characterized as:
A) A 'Quick and Dirty' system
B) A series of versions
C) A method for exploring design alternatives
D) A method for stressing customer satisfaction
E) More explicit testing
Correct Answer:

Verified