Which of the following methodologies might be most appropriate if you have a system project with: somewhat unclear requirements;somewhat unfamiliar technologies;that is complex;reasonably reliable;a short time schedule and high schedule visibility?
A) Waterfall
B) Parallel
C) Iterative
D) System prototyping
E) Throwaway prototyping
Correct Answer:

Verified
Correct Answer:
Verified