Multiple Choice
Given the order-requirement digraph below (with time given in minutes) and the priority list T1, T2, T 3, T4, T5, T6, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require?
A) 15 minutes
B) 16 minutes
C) 17 minutes
D) 18 minutes