Multiple Choice
Use the decreasing-time-list algorithm to schedule these tasks on two machines: How much time does the resulting schedule require?
A) 19 minutes
B) 20 minutes
C) 21 minutes
D) 22 minutes
Correct Answer:

Verified
Correct Answer:
Verified