Multiple Choice
Given the order-requirement digraph below (with time given in minutes) and the priority list T1, T4, T 5, T2, T3, T6, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require?
A) 14 minutes
B) 15 minutes
C) 16 minutes
D) 18 minutes