Use the Following Digraph to Answer Questions

Question 53

Multiple Choice

Use the following digraph to answer Questions
Suppose that a crew can currently complete a job (order-requirement digraph is shown below) in a minimum amount of time. Use the following digraph to answer Questions  Suppose that a crew can currently complete a job (order-requirement digraph is shown below)  in a minimum amount of time.   -If Task T<sub>5</sub> is shortened from 6 minutes to 3 minutes, then what is the maximum amount of time by which the completion time of the entire job can be shortened? A)  It cannot be shortened B)  1 minute C)  2 minutes D)  3 minutes
-If Task T5 is shortened from 6 minutes to 3 minutes, then what is the maximum amount of time by which the completion time of the entire job can be shortened?


A) It cannot be shortened
B) 1 minute
C) 2 minutes
D) 3 minutes

Correct Answer: