Multiple Choice
Given the order-requirement digraph below (with time given in minutes) , apply the critical-path scheduling algorithm to construct a schedule using two processors. How much time does the resulting schedule require?
A) 14 minutes
B) 15 minutes
C) 16 minutes
D) 18 minutes
Correct Answer:

Verified
Correct Answer:
Verified