Use the following digraph to answer Questions
Suppose that a crew can currently complete a job (order-requirement digraph is shown below) in a minimum amount of time.
-If Task T1 is shortened from 7 minutes to 4 minutes, then what is the maximum amount of time by which the completion time of the entire job can be shortened?
A) It cannot be shortened
B) 1 minute
C) 2 minutes
D) 3 minutes
Correct Answer:

Verified
Correct Answer:
Verified