Use the decreasing-time-list algorithm to schedule these tasks on two machines: How much time does the resulting schedule require? 9 minutes, 6 minutes, 3 minutes, 4 minutes, 8 minutes 9 \text { minutes, } 6 \text { minutes, } 3 \text { minutes, } 4 \text { minutes, } 8 \text { minutes }


A) 14 minutes
B) 15 minutes
C) 16 minutes
D) 17 minutes