Multiple Choice
Use the decreasing-time-list algorithm to schedule these tasks on two machines: How much time does the resulting schedule require?
A) 14 minutes
B) 15 minutes
C) 16 minutes
D) 17 minutes
Correct Answer:

Verified
Correct Answer:
Verified