Multiple Choice
Use the following digraph to answer Questions
Suppose that a crew can currently complete a job (order-requirement digraph is shown below) in a minimum amount of time.
-If Task T2 is shortened from 9 minutes to 6 minutes, then what is the maximum amount of time by which the completion time of the entire job can be shortened?
A) It cannot be shortened
B) 1 minute
C) 2 minutes
D) 3 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q89: Give an example of an order-requirement digraph
Q90: Give an example of an order-requirement digraph
Q91: Use the order-requirement digraph below (with time
Q92: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1043/.jpg" alt=" -Use the next-fit
Q93: Use the decreasing-time-list algorithm to schedule
Q95: The worst-fit decreasing (WFD) algorithm for bin-packing
Q96: The first-fit (FF) algorithm never uses more
Q97: Give an example in which six independent
Q98: Choose the packing that results from the
Q99: Why are there several different algorithms for